Tuesday, June 14, 2016

A Tale of Two Ceilings

Have you ever wondered why there are two ways to create a ceiling? It seems like the obvious choice between sketching a ceiling and allowing Revit to automatically create one would be the latter... wouldn't it? Of course for the automatic ceiling to work you have to have bounding elements, therefore in situations where you don't have these elements, i.e. walls, you're going to have to sketch it. For clearly defined spaces where there are walls defining the space, using the automatic ceiling seems like the obvious choice.

Automatic or Sketch

When you create a ceiling, Revit wants to host the boundary of that ceiling to the walls that define the space. It does not matter which method you choose to create the ceiling, Revit will host the boundary of the ceiling to the walls. The difference is when you SKETCH a ceiling in a space with unjoined collinear walls, Revit chooses one to host to leaving the other one free to move. Now you may be thinking this isn't a big deal, but keep reading the payoff is coming.   


Here's the rub

In the design process you may use generic wall types to define a space until you know which wall type you're going to use. Some may have different materials which can result in walls having different thicknesses. Because of this these walls don't always "join" together to make one continuous wall, and they don't always align perfectly. There are two things that occur that will cause this warning. Changing the wall type such that the thickness of the wall changes causing the face to break the collinear alignment with the adjacent wall, and moving one of the walls which also causes the faces of the walls to become misaligned. 


 Save the Ceilings!

Deleting the ceilings could affect the model of anyone who has the architects model linked. Our esteemed engineers host elements to the architecture ceilings all the time, therefore deleting them would leave any hosted elements orphaned. We don't want that. 

If you're not sure which ceilings are affected you can expand the tree in the warning dialog and all the affected elements are listed there. Checking the box and clicking the "Show" button will take you right to the ceiling.








Once you know which ceilings are affected you can fix them. Select the ceiling and choose the Edit Boundary button on the ribbon. It's not a difficult fix, but if you have a lot of ceilings to fix it could get tedious.


I'm a big fan of the automatic ceilings method. It's a fast and efficient way to place ceilings. IMO if you're careful and attentive to the spaces in which you're placing ceilings the automatic method is still the way to go. Having said that, if you feel sketching the ceilings and not having to worry about them failing if you change a wall in some way saves you time, then that should be the method you use.  

Thursday, July 11, 2013

Revit across the internet?

Great post today from Steve over at OpEd. He brings up a good point about trying to make Revit do things it's not really designed to do. Often time these work arounds end up costing you more time and money in the long run. I had similar issue this morning. My firm is currently working with another firm on a project located in a different state but close to one of our offices. The local firm is the prime and we're handling the interiors. At the beginning of the project it was decided that everyone work in the same model and we'd use Revit Server to host the models. If you used Revit Server before you know that working over different networks is very difficult and not really supported by Autodesk anyway. However, we do it because we are gluttons for punishment and because we want the ability to work in the same model. 

This method worked while the model was small and few people were working in it. Once the model grew and more more links were added it became apparent hosting the model in a single location and creating local files over VPN access was the wrong decision. At the worst point it was taking 4.5 hours to open the model. This was not sustainable and of course it disrupted the work flow of all those involved in the project. We then had to brainstorm to figure out the best way to resolve the problem. We settled on creating dead links for the MEP model as well as the structural model which has it's own set of problems. The project is now running somewhat smoothly with 30min. sync times. If it gets worse we're thinking of sending our staff to work from our partners office until the project is done. 

I guess the moral of the story is two fold. Planning is everything and if at all possible don't try to make Revit do what it's not really designed to do.    

Welcome to revitED!

RevitED (Revit Education) and general BIM topics. I've been using Revit now for 11 years, and though I feel I've got a pretty good handle on the software it seems each day I learn something new. I want to share that with the readers of this blog and hope you learn something new as well.